Track Record

1998

Participated in an open bid, permit acquired

2000

First drilling campaign
Confirmed the presence of gas and condensate in all three exploratory wells

2003

Second drilling campaign

2004

2007

Third drilling campaign

2008

Darwin selected as LNG Plant location(2008)

2009

Commencement of onshore and offshore FEED work (2009)

2011

Application for Environmental Approval

Application for Production Licenses

Granted environmental approval from Federal and Northern Territory governments

Liquefied Natural Gas (LNG) sales agreement signed

Offshore EPC / Onshore EPC

2012

FID

Final Investment Decision Executed (January 2012)

Groundbreaking Ceremony of LNG Plant (May 2012)

Project Financing Arrangements Completed (December 2012)

2013

2014

FPSO Keel Laid (February 2014)

Construction Milestone Reached for World's Largest CPF Semi-submersible Platform (April 2014)

Project Half Way Mark Reached (June 2014)

Commencement of 889 Kilometer Pipelay (June 2014)

Floating Production, Storage and Offloading (FPSO) Hull Launched (July 2014)

Completion of Dredging in Darwin, Australia for Shipping, Gas Export Pipeline (August 2014)

2015

Commencement of Development Drilling (February 2015)

Central Processing Facility (CPF) Launched (September 2015)

Completion of Offshore Pipelay (November 2015)

2016

2017

Central Processing Facility (CPF) Sailed Away (April 2017)

2018

Commencement of gas production from the wellhead (July 2018)

Commencement of LNG and condensate shipment (October 2018)

Commencement of LPG shipment (November 2018)

2019

100th LNG cargo shipped (November 2019)

Financial completion achieved (December 2019)